March 2024 Ain Sokhna, Suez Governorate
Ain Sokhna Power Plant Cooling Tower Treatment
Project Overview
A gas-fired power generation facility at Ain Sokhna was experiencing severe scaling in their cooling tower and heat exchangers, causing a 28% reduction in heat transfer efficiency and necessitating emergency shutdowns for cleaning every 3 months. The root cause was inadequate chemical dosing and no Legionella management protocol in place. More Pure designed a comprehensive cooling water treatment program — antiscalant, corrosion inhibitor, biocide — with automated online dosing, continuous ORP and pH monitoring, and a quarterly Legionella risk assessment protocol.
Project Gallery
Technical Details
Application Power plant cooling towers
Cooling Water Volume 8,000 m³ system volume
Challenge Solved 28% efficiency loss + Legionella risk
Program Components Antiscalant + inhibitor + biocide + monitoring
Client Type Gas-fired power generation
Similar Project for Your Facility?
Tell our engineers about your water challenge. We'll prepare a tailored response.
Get a Quote