November 2022 Ain Sokhna, Suez Governorate
Ain Sokhna Industrial Port Facility
Project Overview
A major industrial facility at Ain Sokhna required 2,000 m³/day of process water for cooling and manufacturing operations, with zero tolerance for supply interruptions. More Pure engineered a two-train SWRO system with 100% redundancy — each train capable of meeting full demand independently — along with a 3-day treated water storage buffer. The plant has operated for 18 months without a single unplanned shutdown.
Project Gallery
Technical Details
System Capacity 2,000 m³/day
Configuration Dual-train SWRO (100% redundancy)
Feed Water TDS 44,200 mg/L
Product Water TDS < 350 mg/L
Storage Capacity 6,000 m³ (3-day buffer)
Client Type Heavy industrial facility